Cadishead Way Stage 2 - photographs

View of the North Bank Bridge construction

Cadishead Way Bypass opened Friday 16 September 2005 - 35 weeks ahead of schedule and well within budget.

The project commenced in February 2004 and was schedule to take 120 weeks to complete, however, due to re-sequencing of the works the Bypass will be completed within 85 weeks.

The Cadishead Way Bypass will ease congestion by diverting traffic away from the centre of Cadishead and providing an alternative route to the A57 Liverpool Road, between Brinell Drive, Irlam and Salford’s boundary with Warrington at Glazebrook.

The project involves the building of a 2.4km of single carriageway through difficult ground conditions and will require the construction of a large bridge through a currently disused railway embankment.

Photographs of progress to date are available below, which will be added to on a quarterly basis.

Photographs September 2005

Photographs from:

Quarterly reports are also available to provide more information of the project so far. Also available is information on Community Projects.

This page was last updated on 24 October 2005

This service is provided on behalf of the city council by Urban Vision Partnership

Bookmark this page using:

These sites allow you to store, tag and share links across the internet. You can share these links both with friends and people with similar interests. You can also access your links from any computer you happen to be using.

If you come across a page on our site that you find interesting and want to save for future reference or share it with other people, simply click on one of these links to add to your list.

All of these sites are free to use but do require you to register. Once you have registered you can begin bookmarking. Each of the sites works slightly differently so use the links below to find out which service best suits your needs.

Find out more about social bookmarking at Wikipedia.

Hide this information.

Copyright Salford City Council
Salford City Council, Salford Civic Centre, Chorley Road, Swinton, Salford M27 5AW   Telephone 0161-794 4711
  • 3 star
  • Information about using the Browsealoud reader on this site
Directgov straight through to public services www.direct.gov.uk

http://www.salford.gov.uk/business/design/engineering/highways/cadisheadway-stage-2/cws2-photos.htm
© Copyright Salford City Council 2008.

Improving people's lives   IN Salford