Pupil Place Planning

The increasing demand for primary school places has been widely reported, and is being experienced across the country at both local and national level.

Salford began to experience increased demand for primary places in late 2010. The rise in birth rate, along, with an increase in migration has led to increased and on-going demand for places. Since 2011, with the expansion of existing schools, the local authority has created an additional 5000 primary school places (the equivalent of twenty four 1 Form Entry primary schools). Details of completed school expansions and a citywide school primary area plan can be found below.

Whilst Salford has seen a small increase in secondary pupil numbers this has not been as dramatic as what has been experienced across the primary sector. However, as the growth we have seen at primary school level begins to feed through to the secondary sector, there will be the need to create additional spaces. The local authority is currently looking at future options and details of schemes will be published going forward.

As the growth in primary school numbers begins to feed through to the secondary sector, going forward, there will be a need to create additional secondary capacity. Details of school expansions completed to date can be found by clicking on the planning area links below.

  • In terms of future expansions, the local authority will continue to develop options to support a sustainable school estate and will continue to:
  • Meet its statutory duty for providing sufficient schools places across all areas of the city through forward planning and providing, creative, cost effective solutions;
  • Support the creation of neighbourhoods of choice and sustainable communities, where families choose to live, stay, work, and send their children to school;
  • Ensure that parental preferences are met to the greatest extent, providing access to a choice of high quality schools within their local area and enabling siblings and families to stay together;
  • Continue to deliver building solutions which support curriculum delivery and contribute to the City Council’s vision for transforming educational outcomes for all children and young people across the city;
  • Strive to ensure that no pupils (other than by choice), are required to travel further than the statutory distance;
  • Work closely with schools and stakeholders including our Greater Manchester counterparts to deliver agreed outcomes.

Area 1 - Little Hulton and Walkden

2011 Project

  • St Edmunds RC – Additional one class solution
  • Hilton Lane Community – Additional one class solution

2012 Project

  • Peel Hall Community – Additional one class solution
  • St Paul’s Peel CofE – Additional one class solution

2013 Project

  • Peel Hall Community - Permanent increase from a 1 FE to a 2 FE Primary School via internal re-configuration and small extension
  • Bridgewater Community- Permanent increase in capacity from a 1FE to a 1.5FE via a 4 class room modular build

2014 Project

  • Bridgewater Community– Increase the existing school by a full 1FE via 5 classroom extension and internal reconfiguration
  • St Andrews CE – Additional one class solution (+8 reception)

2015 Project

  • St Paul’s CE Heathside – Phase I – Increase the existing school by a full 1FE, starting with Phase 1 the conversion of the former Children’s Centre accommodation for KS 2.
  • St Andrews CE – expand one class solution to 30 (+22) additional capacity through internal re-organisation work to library.
  • Wharton – Additional one class solution

2016 Project

  • St Paul’s CE Heathside – Phase II – Increase school to a full 2FE, Continue to provide addition accommodation via extension to complete the project.
  • North Walkden – Increase PAN to 30 per class (+3 per yr group)
  • Wharton CP – Additional one class 30 Reception.

2017 Proposed Project

  • Phased increase of Wharton CP to a permanent 2FE

2018 Project

  • Wharton - Three classroom expansion to become full two forms of entry (complete)
  • Harrop Fold High School – One classroom expansion to increase Pupil Admission Number

Area 2 – Boothstown, Worsley and Ellenbrook 

2011 Project

  • Mesne Lea Community – Additional one class solution
  • James Brindley Community – Additional one class solution

2012 Project

  • Ellenbrook Community – Additional one class solution
  • Mesne Lea Community – Additional one class solution

2013 Project

  • St Marks CE – Permanent Increase from a 1.5FE to a 2FE via 4 class room modular extension.
  • Mesne Lea Community – Additional one class solution

2014 Project

  • Mesne Lea Community – require additional one class for Sept 2014 via existing class space/temporary accommodation

2015 Project

  • Ellenbrook Community – Permanent Increase from a 1FE to a 2FE via 8 class base 2 storey extension
  • Mesne Lea Community – New build complete through Education Funding Agency Sept 2015.(2FE)

2016 Project

  • James Brindley - Additional one class solution (10 Children - Reception)

2017 Proposed Project

  • Mesne Lea – SEND space created to assist with the SEN needs throughout Salford

Area 3 – Irlam and Cadishead

2011 Project

  • Cadishead Community – Additional one class solution
  • Moorfield Community – Additional one class solution
  • Filddlers Lane Community – Additional one class solution

2012 Project

  • Cadishead Community – Additional one class solution
  • Fiddlers Lane Community – Additional one class solution
  • St Teresa’s RC - Additional one class solution

2013 Project

  • Cadishead Community – Permanent Increase from a 1.5FE to a 2FE with use of existing
  • Fiddlers Lane Community – Permanent increase from a 1FE to a 2FE via internal reconfiguration and the use of adjacent building
  • St Mary’s CE – Additional one class solution

2015 Project

  • Fiddlers Lane Community – Additional one class solution to support 2FE permanent expansion utilising the children’s centre accommodation
  • Moorfield CP – Expansion to develop an ASC unit at primary level, Silver Street building

2017 Project

  • Springwood Special School - Craig Hall Campus – Expand Springwood Special School

2018 Project

  • Springwood 2 Craig Hall - 1 classroom expansion at site to increase Pupil Admission Number via internal reconfiguration
  • Moorfield ASD (Autism Spectrum Disorder) provision – refurbishment of old nursery block

Area 4 – North Swinton

2012 Projects

  • Mossfield Community – Additional one class solution

2013 Projects

  • Mossfield Community – Permanent increase from a 1 FE to a 2 FE primary via internal reconfiguration

2014 Project

  • Mossfield Community – Additional one class solution for additional 15 reception pupils

2015 Project

  • Expansion of Grosvenor Road Primary in the adjacent planning area to support need for September 2015

2016 project

  • Clifton Centre – Increase PAN (proposed New Build via the EFA 2018). PRU

2018 Project

  • Clifton Centre Pupil Referral Unit - complete rebuild via the PSBP 2 programme, DFE led

Area 5 – South Swinton

2011 Projects

  • Moorside Community – Additional one class solution
  • Grosvenor Road Community – Additional one class solution (2016 Moved to Planning Area 8)

2012 Projects

  • St Mary’s RC – Additional one class solution
  • St Charles RC – Additional one class solution
  • Moorside Community – Additional one class solution

2013 Projects

  • Moorside Community - Permanent increase from a 1 FE to a 3 FE primary via new build

2014 Projects

  • Grosvenor Road – Additional one class solution

2015 Projects

  • Grosvenor Road Community - Permanent increase from a 2 FE to a 3 FE primary via 7 class base 2 storey extension

2016 Project

  • Move Grosvenor Road provision to Planning Area 8

2017 Project

  • The Deans Community - Permanent increase from a 1 FE to a 2FE primary via relocation and new 2FE build

2018 Project

  • Springwood Swinton – 1 class room expansion to increase Pupil Admission Number via internal reconfiguration

Area 6 – North Eccles

2012 Projects

  • St Gilberts RC – Additional one class solution
  • Westwood Park Community – Additional one class solution

2013 Project

  • Monton Green Community – Increase from 1 .5 FE to a 2FE via a 4 class room modular build extension
  • St Gilberts RC – Additional one class solution

2014 Project

  • Westwood Park Community - Additional one class solution
  • Monton Green Community - Increase from 1 .5 FE to a 2FE via a 4 class room modular build extension

2015 Project

  • Alderbrook and New Park - additional KS2/3 Provision located at Alderbrook

2016  Project

  • Westwood Park - additional one class solution class

Area 7 – South Eccles

2012 Project

  • Beech Street Community – Additional one class solution

2013 Project

  • Lewis Street Community - retained school to allow permanent phased increase from 1 FE to 2 FE via internal reconfiguration and small class room extension - Additional one class solution created to provide places for 2013

2014 Proposed Project

  • Lewis Street – Phase I works (KS1 internal works and 2 class base extension)
  • Godfrey Ermen – Additional one class solution
  • Beech Street – Additional one class solution

2015 Project

  • Lewis Street – Phase II  works (KS2 internal works/external areas)
  • Godfrey Ermen – Phase I works (Permanent expansion from 1.5FE to a 2FE)

2016 Project

  • Godfrey Ermen – Phase II works (Permanent expansion from 1.5FE to a 2FE)
  • Holy Cross and All Saints – Additional one class solution for Proposed permanent expansion from a 1FE to a 1.5FE

2017 Project

  • Holy Cross and All Saints – permanent expansion from a 1FE to a 1.5FE 

2017 Project

  • Holy Cross and All Saints – permanent expansion from a 1FE to a 1.5FE.

2018 Project

  • Godfrey Ermen – internal reconfiguration to provide SEND facilities
  • Alderbrook – SEMH (Social, Emotional, Mental Health) classroom expansion

Area 8 - Claremont

2011 Project

  • St Luke’s RC – Additional one class solution
  • Summerville Community – Additional one class solution

2012 Project

  • Summerville Community – Additional one class solution
  • St Luke’s RC – Additional one class solution

2013 Project

  • St Johns CE* – Increased capacity from a 1 FE to a 2FE via new 1FE new build located on the Former Oakwood Site.  Additional one class solution created.
  • St Luke’s RC – Increased capacity from a 1.5FE to a 2FE via 4 class room extension.  (Additional one class solution class delivered in the interim to meet demand)

2014 Project

  • St John’s CE – Permanent expansion from 1FE to a 2FE via split site solution

2015 Project

  • Summerville – Additional one class solution class

2016 Proposed Project

  • Summerville – Conversion of the ICT suite to a classroom, to support previous additional class solutions and provision of ‘leaf’ type provision within the former children’s centre

Area 9 – Weaste and Langworthy

2011 Project

  • Lark Hill Community - Additional one class solution

2012 Project

  • Lark Hill Community - Additional one class solution
  • St Luke’s CE – Additional one class solution

2013 Project

  • Lark Hill Community – Permanent increase from a 1 FE to a 2 FE via internal configuration and class room extensions
  • St Luke’s CE – Additional one class solution

2014 Project

  • St Luke’s CE – Additional one class solution

2015 Project

  • St Luke’s CE – Permanent increase from 1FE to a 2FE. Bulge Class initially on the current site.  Relocate for 2016
  • Willow Tree – Additional one class solution
  • Lark Hill – Additional one class solution

2016 Proposed Project

  • Increase Lark Hill Community School – Permanent expansion from 2 – 3 FE with additional SEN facilities
  • St Luke’s CE – Permanent increase from 1FE to a 2FE.  Achieved via relocation to a new build 2FE on the former All Hallows site

Area 10 – Broughton and Kersal

2012 Project

  • Lower Kersal Community – Additional one class solution

2013 Project

  • The Friars Community – Phased increase from a 1FE to a 2FE - Additional one class solution  delivered for 2013

2014 Project

  • The Friars Community – Phase I – Adaptation of former youth centre to accommodate foundation unit (nursery and reception)

2015  Project

  • The Friars Community – Phase II – Internal reconfiguration for creation across KS1 classes

2016 Proposed Project

  • The Friars Community – Phase III – Internal reconfiguration for creation across KS2 classes, extension to Hall

Area 11 - Ordsall

2011 Project

  • Holy Family RC – Additional one class solution

2012 Project

  • St Philips CE – Additional one class solution

2013 Project

  • St Philips CE – Phased Increased from a 0.5 FE to a 1 FE- Phase I works internal reconfiguration

2014 Project

  • St Philips CE – Phased Increased from a 0.5 FE to a 1 FE- Phase I works internal reconfiguration
  • Primrose Hill Community – Additional one class solution

2015 Project

  • Primrose Hill Community – Increase from a 1.5 FE to a 2 FE via use of community rooms and internal re-configuration

Area 12 - Border

2011 Project

  • St Thomas of Canterbury RC – Additional one class solution
  • Brentnall Community – Additional one class solution

2012 Project

  • Brentnall Community – Additional one class solution

2013 Project

  • Marlborough Road (Academy) – Additional one class solution
  • St Thomas of Canterbury – Permanent increase from a 1 FE to a 2 FE via internal reconfiguration

2014 Project

  • Marlborough Road (Academy) – Additional one class solution.

2015 Project

  • Brentnall Community – Additional one class solution via the use of 2 class base modular

2016 Proposed Project

  • Brentnall Community - Additional class solution with temporary solution ready for September 2017 intake.
  • Broughton Jewish Cassel Fox – Additional one class solution

2017 Project

  • Broughton Jewish Cassel Fox - Permanent increase from a 1 FE to a 2 FE via internal alteration and expansion.

2018 Project

  • Brentnall Community - Additional class solution with temps ready for permanent increase 2017

 