Upcoming roadworks in Peel Green – early 2026

Over the coming months, a series of essential improvement works will be carried out in the Peel Green area. These works are designed to:

  • Upgrade utilities to strengthen local infrastructure
  • Introduce flood prevention measures to improve resilience against extreme weather
  • Deliver safety improvements for all road users

To complete these projects, various traffic restrictions will be in place at different stages. Full details are outlined below.

If you have any questions or need further information, please contact the relevant person listed for each project.

United Utilities

Date: 2 January 2026

Location: Liverpool Road, Winton

Traffic management: Lane closure near Sealand Drive between 10am and 2pm

Details: Routine jetting, inspection, and CCTV surveillance works on sewer assets on behalf of United Utilities.

Contact: ipsum.trafficmanagement@ipsum.co.uk 

Serconnect

Date: 5 January to 8 February 2026

Location: Liverpool Road (Eccles and Irlam)

Traffic management:

  • 24-hour lane closures from Barley Farm to Junction 11 roundabout
  • Road narrows on the Eccles side from Lansdale Street to Junction 11 roundabout

Details: HV electrical works on behalf of Ionity to power EV chargers at Barley Farm.

Contact: jason.moss@serconnect.co.uk 

Salford City Council

Date: 12 January to 19 January 2026

Location: Barton Lane, Eccles

Traffic management: Road closure to repair surface water drop shafts

Details: Trial holes on the sewer to investigate blockages within the surface water drainage system. Upgrades to low bridge warning signs also planned.

Salford City Council 

Date: 9 February to 20 February 2026

Location: Liverpool Road, Eccles 

Traffic management:

  • One-way road closure: 8pm to 6am on 9, 10, 16, 17 and 18 February
  • Multi-way signals: 9.30am to 3.30pm on 11, 12, 13, 19 and 20 February

Details: Road resurfacing

United Utilities

Date: 2 March to 19 April 2026

Location: Peel Green Road (closed 24/7 at the junction with Haddon Road)

Details: Installation of a new 1200mm diameter drainage pipe to increase network capacity and address flooding issues on Peel Green Road.

Contact: UU Customer Helpline: 0345 672 3723

Project Reference: 80065871