Upcoming roadworks in Peel Green – early 2026

Over the coming months, a series of essential improvement works will be carried out in the Peel Green area. These works are designed to:

  • Upgrade utilities to strengthen local infrastructure
  • Introduce flood prevention measures to improve resilience against extreme weather
  • Deliver safety improvements for all road users

To complete these projects, various traffic restrictions will be in place at different stages. Full details are outlined below.

If you have any questions or need further information, please contact the relevant person listed for each project.

United Utilities

Date: 2 March to 19 April 2026

Location: Peel Green Road (closed 24/7 at the junction with Haddon Road)

Details: Installation of a new 1200mm diameter drainage pipe to increase network capacity and address flooding issues on Peel Green Road.

Contact: UU Customer Helpline: 0345 672 3723

Project Reference: 80065871

Serconnect

Date: 16 March to 29 March, including overnight works

Location: Liverpool Road (Eccles and Irlam)

Traffic management:

  • 16 March to 27 March: 24-hour lane closures from Barley Farm to Junction 11 roundabout
  • 16 March to 22 March: footway works, no impact on carriageway
  • 21 March to 22 March: three-way signals at Argosy Drive junction
  • 23 March to 29 March: lane closures for overnight works between 8pm to 6am, except 27 March and 29 March when works will be 11pm to 6am

Details: HV electrical works on behalf of Ionity to power EV chargers at Barley Farm (remedial works)