Sign in to access your Salford customer account, or see our other accounts.

Sign in or register for an account

Reversion applications

If you have appointed a Registered Building Control Approver (RBCA), formerly known as an Approved Inspector, to undertake the building control function for your building work, the local authority is not normally responsible for assessing compliance with the Building Regulations whilst the Initial Notice remains in force.

However, where building work has commenced and an Initial Notice is cancelled or ceases to be in force before a Final Certificate has been accepted, responsibility for the building control function will normally revert to the local authority. In these circumstances, a Reversion application may be required to enable the local authority to continue the building control process.

Before proceeding with an application, you should ensure that Reversion is the most appropriate option for your circumstances. In some cases, an alternative Registered Building Control Approver may be able to take over the project. If you are uncertain, you should seek professional advice.

Further guidance

Further information regarding reversion, cancellation notices and transfers is available from:

Reversion process

Step 1 - Submit your application

Complete and submit the Reversion Application Form together with all available information relating to the project.

Download the Reversion application form

What information should I provide?

It is your responsibility to demonstrate that the requirements of the Building Regulations have been met.

To enable Building Control to assess compliance, you should provide as much information as possible on submission of your application. This is likely to include:

  • Inspection records from your Registered Building Control Approver.

  • Existing and proposed drawings.

  • Structural calculations and design information.

  • Specifications.

  • Technical reports.

  • Certificates and test results.

  • Details of any identified contraventions and how they have been remedied.

Depending on the nature, complexity and stage of the project, additional information may be required.

How do I submit my application?

The completed application form and supporting information should be submitted by email to:

building.control@salford.gov.uk

Step 2 - Review and fee assessment

Building Control will undertake an initial review of the information submitted. You will be notified of the applicable fee following this review, and will be provided with payment instruction.

The application will not progress until payment is made in full. Please note all fees are non-refundable.

Step 3 - Validation and technical review

Once payment has been received, the application will be validated and allocated to a Building Inspector for review. This review will usually be undertaken with eight weeks of validation. You may need to factor this timescale into your project planning.

Where necessary, additional information may be requested before the application can progress further.

Step 4 - Inspection and assessment

Once sufficient information has been provided and the application has been reviewed, Building Control will advise when a site inspection can be arranged.

The site inspection will form part of the council's assessment of compliance with the Building Regulations. Where compliance cannot be established from the information available and inspection findings, Building Control may require:

  • Additional information or evidence.

  • Opening up of completed works.

  • Testing of construction elements.

  • Remedial works.

  • Further inspections.

Step 5 - Completion and certification

Once the building work has been completed, all required inspections undertaken, and Building Control is satisfied that compliance with the Building Regulations has been demonstrated, a Completion Certificate will be issued.

Where outstanding matters remain, Building Control may require additional information, testing, opening-up works or remedial works before a final decision can be made.

Where compliance cannot ultimately be demonstrated, a Completion Certificate cannot be issued. In such circumstances, the local authority may need to consider further regulatory action.

Important information

  • Acceptance of a Reversion application does not constitute approval of the works.

  • Building Control will assess compliance based upon the information available, site inspections and any additional evidence obtained during the application process.

  • The responsibility for demonstrating compliance with the Building Regulations remains with the person/s undertaking the work.

  • Site inspections will not normally be undertaken until the technical review of the application has been completed.

  • Issue of the Building Regulations Completion Certificate is evidence (but not conclusive evidence) that the requirements of the Building Regulations have been complied with.