Current traffic regulation orders

Please refer to the notes below for guidance on the order making process.

November 2017

October 2017

September 2017

August 2017

July 2017

June 2017

May 2017

April 2017

March 2017

February 2017

January 2017

December 2016

November 2016

October 2016

September 2016

August 2016

June 2016

May 2016

April 2016

March 2016

February 2016

January 2016

The order making process

A decision is usually required by the Planning and Transportation Regulatory Panel that the order is needed.

At this time the order is advertised and people are given 21 days to object to its installation. Traffic regulation orders currently being advertised can be viewed further down this page. At the end of this period a report is taken back to the panel which details the objections and they determine whether or not to introduce it.

If they decide that the order should be introduced, the required works such as lining and signing are carried out and then the order is 'sealed'. Seven days later it can be enforced.

Double yellow lines no longer require a 24 hour 'no waiting' plate, they can be enforced on their own.

Sometimes, however, temporary orders or experimental orders are introduced which require a slightly different process but still gives people an opportunity to put forward their views.

This page was last updated on 16 November 2017

Live Chat Software by Click4Assistance UK